ALEKSEEVSKA OIL MILL – C.I.S.
Customer : GROU

Customer : JSC EFKO Alekseevska – Russia

General contractor :
De Smet Engineers & Contractors.

Scope of works :
Design, supply, supervision of installation and commissioning.

Industrial operation :
Extraction : December 1997
Refining : December 1999
Fractionation : April 2002.

Main sub-contractors involved :
De Smet Technologies and Services - Belgium

Plant capacity :
Crushing : 300 MTPD
Refining : 230 MTPD
Fats refining/Fractionation/Hydrogenation/Interesterification 100 MTPD

Processing units :
- Oil refining plant complete with physical /
- chemical refinery unit,
- bleaching unit, winterising unit and deodorising unit
- Hydrogenation & post treatment unit
- Interesterification unit
- Deodorizing unit
- Double dry fractionation unit
- Tank farms
Utilities :
- Hydrogen production unit
- Nitrogen production unit
- Laboratory pilot unit
- Tank farms